Samsung Vietnam proposes direct purchase of renewable energy

In this article (5)
Electronics giant Samsung Vietnam has proposed that it joins a trial program to purchase power directly from renewable power plants instead of monopoly distributor Vietnam Electricity.
Choi Joo Ho, CEO of Samsung Vietnam, submitted the proposal to the Ministry of Industry and Trade last week. He asked that the company participates in the Direct Power Purchase Agreements (DPPA) policy that is being studied for a three-year trial.
Three to four other big companies also want to join the program, a person familiar with the matter told VnExpress.
The program will allow manufacturing companies with a minimum of 22-kilovolts power lines to negotiate and buy directly from solar and wind power plants.
In the first three years, when the policy will be trialed, the customer needs to buy at least 80 percent of the agreed amount of power.
Solar and wind farms with a capacity of 30 megawatts or more can sign these agreements and need to begin commercial operation within nine months of joining the pilot program.
The program with a total capacity of around 1,000 megawatts is set to start this year and run until 2023. At the end of the trial period, the ministry will review it and take a decision on making the arrangement permanent.
The program is being considered amid the challenges solar power plants face in running at full capacity due to the limited capacity of the country’s transmission lines. Vietnam is set to cut up to 1.74 billion kilowatt-hours of renewable energy in the second half this year to deal with national grid overload, Vietnam Electricity, has announced.
Questions & Answers
Q.Which government body received Samsung Vietnam's proposal to join the direct power purchase program?
Which government body received Samsung Vietnam's proposal to join the direct power purchase program?
Samsung Vietnam's CEO, Choi Joo Ho, submitted the proposal to the Ministry of Industry and Trade. The ministry is currently studying the Direct Power Purchase Agreements policy for a three-year trial.
Q.What capacity must renewable power plants have to participate in the proposed direct purchase agreement trial?
What capacity must renewable power plants have to participate in the proposed direct purchase agreement trial?
Solar and wind farms must have a capacity of 30 megawatts or more to sign these agreements. They also need to begin commercial operation within nine months of joining the pilot program.
Q.What is the total planned capacity for the direct power purchase trial program?
What is the total planned capacity for the direct power purchase trial program?
The program is set to have a total capacity of around 1,000 megawatts. It is expected to start this year and run until 2023, after which it will be reviewed.
Q.Why is Vietnam considering this new power purchase programme?
Why is Vietnam considering this new power purchase programme?
The programme is being considered due to the challenges solar power plants face, such as limited transmission line capacity. Vietnam Electricity also announced planned cuts to renewable energy this year due to grid overload.
Reader pulse
Samsung's DPPA proposal:
21,154 votes so far