The developer of the Java 1 combined-cycle power plant, claimed to be the biggest of its kind in Southeast Asia, has granted an engineering, procurement and construction contract worth US$900 million to a consortium consisting of General Electric (GE), Samsung C&T and PT Meindo Elang Indah Indonesia.

PT Jawa Satu Power, a joint venture between state-owned energy giant Pertamina and Japan’s Marubeni and Sojitz Corporation, is currently in the process of developing the Java 1 power plant in Karawang, West Java, Indonesia, with a total investment value of around $1.8 billion.

The Java 1 facility, expected to commence operations in mid-2021, will have a total capacity of 1,760 megawatts (MW), enough to supply electricity to about 11 million households in Indonesia.

“Efficiency in power plants is important to maintain competitive and affordable electricity rates for the public. Our high-efficiency gas turbine called GE 9HA.02 and asset performance management software will play their role for those purposes,” GE Indonesia president and CEO Handry Satriago said in a statement on Thursday.

Jawa Satu Power president director Ginanjar has high hopes that GE’s gas turbines will provide reliable and clean energy to the public.

It has also signed a 25-year agreement with GE Power Services, which provides operations and maintenance management for gas plant assets.

Questions & Answers

Q.

Which companies formed the consortium awarded the engineering, procurement and construction contract for the Java 1 power plant?

A.

The contract was granted to a consortium comprising General Electric (GE), Samsung C&T, and PT Meindo Elang Indah Indonesia.

Q.

What is the total investment value for the Java 1 power plant development?

A.

The total investment value for developing the Java 1 power plant is approximately $1.8 billion.

Q.

When is the Java 1 power plant expected to begin operations?

A.

The Java 1 facility is expected to commence operations in mid-2021.

Q.

What is the generating capacity of the Java 1 power plant?

A.

The Java 1 power plant will have a total capacity of 1,760 megawatts, capable of supplying electricity to about 11 million households.

Reader pulse

Does reliable power impact retail expansion?

18,918 votes so far

Weekly Briefing

Asia's retail intelligence, in your inbox

Tuesday, Thursday and a Saturday Weekly Wrap: the retail stories, numbers and moves that mattered across Asia. Nothing else, and you can unsubscribe in one click.

  • Top industry moves and market shifts
  • Weekly data-driven analysis from across Asia
  • Tuesday, Thursday and the Saturday Weekly Wrap

Read by retail operators, investors and brand teams across Asia.

Protected by a quick human check. No spam, ever. Unsubscribe in one click.

SecureGDPR ready